Commonwealth Avenue Construction Update: July 23 to August 3

Commonwealth Avenue from Park Avenue to Edinburgh Avenue

Please be advised that waterline service connections will be installed from the new watermain to residences and businesses in the areas of Commonwealth Avenue (civic numbers 11 – 45), Park Avenue (civic number 249) and Edinburgh Avenue (civic number 2) from July 23 to July 27.  East and west side lane closures will occur during this time, however two lanes of traffic will be maintained.

During this time, residents and businesses will lose water service for one (1) hour until the service line connections from the (residence/business) to the watermain are completed.  The Contractor will provide 24 hour notice to residents and businesses in this area.

Commonwealth Avenue from Sunrise Avenue and St. Andrews Avenue

Please be advised that sanitary and storm sewers installation will occur in the centre lane of Commonwealth Avenue in the area of Sunrise Avenue to St. Andrews Avenue from July 23 to August 3. Centre lane closures will occur during this time period however two lanes of traffic will be maintained.

Commonwealth Avenue from Emberley Place and Civic Number 113 Commonwealth Avenue

Please be advised that sanitary and storm sewers installation on the east side of Commonwealth Avenue in the area of Emberley Place from July 23 to August 3. East side lane closures will occur during this time period.