Commonwealth Avenue Construction Update (Sept 4-14)

Please note the following work will be taking place on Commonwealth Avenue over the next two weeks (Monday, September 4th to Friday, September 14th).

Commonwealth Avenue between Ruth Avenue and Edinburgh Street

Sanitary and Storm Sewers installation will continue in the centre lanes. One lane of traffic each side for north and south bound Commonwealth Avenue traffic. One team working from Ruth toward Centennial, and a second team working from Edinburgh toward Centennial. Stop and go traffic may be necessary at times.

Commonwealth Avenue between Smallwood Drive and Francis Street

Construction continues to prepare the west side of the road for base course. There will be two lanes of traffic on the east side.

Commonwealth Avenue and Smallwood Drive Intersection

The storm sewer culvert installation continues diagonally across the Commonwealth Avenue-Smallwood Drive intersection. Traffic restrictions as follows:

  • Commonwealth Avenue south bound: through traffic only for week of Sept 4-7; through and right turn only Sep 10 – 14.
  • Commonwealth Avenue north bound: through and right turn traffic only.
  • Smallwood Drive: right turn only at Commonwealth, both directions.