Commonwealth Avenue Paving – Starting May 27th

Paving is scheduled to begin on Commonwealth Avenue on Monday, May 27th, 2019 and is expected to last six weeks.

Note the following schedule, subject to change:

Week of May 27th – Site preparation

Week of June 3rd – Paving from Francis Street to Smallwood Drive (2 weeks)

Week of June 17th – Paving from Smallwood Drive to Glendale Avenue (2 weeks)

During this time, please expect lane reductions which may result in minor traffic delays.

Please drive carefully.