Construction Update – Fourth Street

The Fourth Street Reconstruction project is in progress. Throughout the length of the project, we are committed to ensuring residents have full vehicular access from Ruth Avenue, Roland Drive, and Sunrise Avenue. Flagspeople and signage have been assigned to these areas to assist drivers and pedestrians to safely enter and exit Fourth Street.

Armstrong Crescent still remains a one-way street during this construction. Please follow signage and directions from flagspeople throughout Fourth Street to safely navigate the ongoing work.

WORK ZONE 1 & 2
Replacement of sanitary and storm sewer is ongoing in both work zones and expected to continue until mid-June. We will continue to provide residents with updates as the project moves forward.

SERVICE DISRUPTIONS
Please note there may be instances of temporary disruption to power and/or water services to allow for completion of ongoing work. If this is necessary, we will provide residents with advance notice.

If you have any questions or concerns, please email engineeringservices@mountpearl.ca or call 709-748-1016.

Thank you for your ongoing patience and cooperation.