Construction Update – Sunrise Avenue and Second Street

CONSTRUCTION IS ALMOST COMPLETE!

The schedule over the next 5 weeks is estimated as follows:

Week of May 27 – Sanitary sewer, road grading, gravel base, curbs, and gutters

Week of June 3 – Sanitary sewer, sidewalks, curbs, gutters, and gravel base

Week of June 10 – Sidewalks, curbs, gutters, and gravel base

Week of June 17 – Completion of concrete work, base course paving

Week of June 24 – Surface course paving, final landscaping and cleanup

What to expect during this time:

  • There may be short-term water outages throughout the construction period. When possible, notice will be provided to you in advance.
  • During concrete work (sidewalks, curbs) and paving, there will be interruptions to your driveway access. We will notify and coordinate with you on an individual basis.
  • Lane closures will be required and flag persons will be on-site.

We are working diligently with our engineering consultant (DMG Consulting Ltd.) and contractor (Weirs Construction Ltd.) to complete this work safely and on schedule. We apologize for the inconvenience and disruption caused by this construction.

If you have any questions, please contact us directly at 709-748-1016.

We look forward to an upgraded Sunrise Avenue and Second Street!

DMG Consulting Ltd. 709-466-7706 or 709-424-7471
Weirs Construction Ltd. 709-368-4081