Road Safety & Traffic Calming

To improve safety and quality of life in our community, the City of Mount Pearl has taken a proactive approach to traffic safety, with our Traffic Calming Policy. 

This policy outlines how we assess and respond to traffic concerns. It provides a clear and consistent process for engaging with the community and making our streets safer. The policy is built on transparency, evidence-based decision-making and community input.

Traffic Calming Policy [PDF/218KB]

Traffic Calming Requests

Under the Traffic Calming Policy, residents can submit a traffic-calming request to express concerns about traffic related issues in their area.

Traffic Calming Request Form

Traffic Calming Policy Procedure

an info graphic of the Traffic Calming Policy Procedure

To implement traffic-calming measures, we follow the procedure outlined in the Traffic Calming Policy:

  1. Resident request: the traffic-calming process begins when someone submits a concern using the Traffic Calming Request Form.
  2. Initial screening: City engineering staff review the request against various criteria, to determine if the requested street is a good candidate for traffic-calming.
  3. Ranking requests: Staff use a scoring matrix to allocate points for each request. This helps the City further identify where traffic-calming measures can make the most impact.
  4. Master Priority list: Each request is then included in a staff managed database, with results from the initial screening and the ranking. This list provides Council as staff with a risk based list of potential projects.
  5. Resident survey: Before moving forward with traffic-calming measures, residents and businesses on the roadway will have an opportunity to provide input. Requests need at least 60% support from the survey to move forward.
  6. Design development: Solutions must be tailored to fit each specific street and conditions, so projects are designed to address the unique challenges of their location.
  7. Council approval: After the initial design is complete, the project plan is submitted to Council for approval.
  8. Detailed design, tendering and construction: If the project plan is approved, staff will proceed with detailed design, call for tender, award, and construction of the traffic-calming measure.
  9. Implementation and monitoring: After six months, the City will review the initial request and monitor the new traffic-calming measure to ensure it is addressing the concern.